1. Write
briefly about
(a)
Types of contract’s
(b)
Contract documents
2. Define
specifications? Explain detailed specification of I class brick work.
3. A
building recently constructed costing of 16,00,000/-.measuring 120sq.m in a big
city prevailing rate of land is 6000/m2. Determine the net rent on
the property.outgoing’s are 42000/-.per year.net rent returns’ expected by the owner on building at
5%& on the land 3.5%.
4. Calculate
the rate of 20mm thick plastering of 1:6-unit 1sqm take -100sqm.
Rate of material’s:
Cement-325/bag
Sand-2000/m3
Labours:
Mason-525/day
Mazdoors-350/day
Bhisti-250/day